17-12-2009 |
 |
|
| |
|
 |
Corewall in progress at 82nd floor in progress |
| |
|
|
|
 |
| |
 |
17-12-2009 |
 |
|
| |
|
 |
Slab at 80th floor under progress |
| |
|
|
|
 |
| |
 |
17-12-2009 |
 |
|
| |
|
 |
Curtain wall in progress at 50th floor |
| |
|
|
|
 |
| |
 |
17-12-2009 |
 |
|
| |
|
 |
ACP cladding in progress at lower floors
|
| |
|
|
|
 |
| |
 |
17-12-2009 |
 |
|
| |
|
 |
Drainage & HVAC risers in progress at 64th floor |
| |
|
|
|
 |
| |
 |
17-12-2009 |
 |
|
| |
|
 |
HVAC ducting works in progress at 57th floor |
| |
|
|
|
 |
| |
 |
17-12-2009 |
 |
|
| |
|
 |
Drainage piping works at 68th floor |
| |
|
|
|
 |
| |
 |
17-12-2009 |
 |
|
| |
|
 |
Fire Fighting piping works in progress at 58th floor |
| |
|
|
|
 |
| |
 |
17-12-2009 |
 |
|
| |
|
 |
Blockwork in progress at 58th floor |
| |
|
|
|
 |
| |
 |
17-12-2009 |
 |
|
| |
|
 |
GI studs for Gypsum partition in progress at 61st floor |
| |
|
|
|
 |
| |
 |
17-12-2009 |
 |
|
| |
|
 |
False ceiling works in progress at 54th floor |
| |
|
|
|
 |
| |
|
 |
 |
| |
 |
|
 |
|
|
|
|